How Long Does an Interior Design Project Take in Scottsdale?

by | Nov 27, 2026 | Interior Design Tips, Residential Interior Design, Scottsdale Interior Design Projects

Every Living with Lolo project runs in phases: design, then construction if there is any, then ordering and delivery, then a one-day install. All-in, from the first design meeting to the day you walk in, a furnishing project takes about 6 to 8 months, a remodel about the same because furniture is ordered during construction, and a new build 12 to 24 months. The phase that usually sets the pace is not construction. It is furniture lead times, which is why how early the design is approved matters more than the size of your Scottsdale home.
This guide breaks each type of project into its phases, gives the all-in total from start to finish, shows where the time actually goes and explains how we plan backward from the date you want to be back in Arizona. It is written from the questions our clients ask on their first call, including "Is that typically a year plus process?" and "By October would be great. Is that realistic?"

How long does interior design take for each type of project?

Here is the timeline we give every client on the first call, phase by phase, with the all-in total in the last column. Remodels and new builds include furnishings, so the all-in total covers the whole home, not just construction. In a remodel or new build, furniture is ordered while construction is underway, so the all-in total is shorter than the phases added together.
Living with Lolo project timelines by phase
Project typeDesignPermits and constructionOrdering and deliveryInstallAll-in, start to finish
Furnishing onlyAbout 6 weeks (concepts, selections and approvals)None4 to 6 months (furniture lead times set the pace)One day (the reveal)About 6 to 8 months
Remodel with furnishingAbout 6 weeks4 to 6 months; permits pulled in-houseDuring construction, in parallelOne day, after construction6 to 8 months, any size
New buildAbout 6 weeksPermits up to 6 months, then construction up to 1 yearDuring construction, in parallelOne day, after completion12 to 24 months

Each project type, phase by phase

  1. Furnishing only: about 6 to 8 months all-in. About 6 weeks of design (concepts, selections and approvals), then 4 to 6 months of ordering and delivery, because furniture lead times set the pace, then a one-day install: the reveal. This is for a home that does not need construction. This is the path for many second homes and new builds in Scottsdale and Paradise Valley. Furnishing starts at $75K, with a three-room minimum.
  2. Remodel with furnishing: 6 to 8 months all-in, any size. A primary bath, several rooms or a whole home. (A large kitchen remodel on its own is shorter: about 4 to 6 months all-in.) Design comes first, about 6 weeks. Then permits, pulled in-house under our Arizona ROC #347577, and 4 to 6 months of construction. We order furniture as soon as you approve the design, so ordering and delivery happen during construction. Install then takes one day once construction is done. That is why a remodel lands at about the same all-in time as a furnishing project: the furniture runs in parallel with construction instead of after it.
  3. New build: 12 to 24 months all-in. We work alongside your architect and builder, or design and build the home ourselves. Design takes about 6 weeks. Permits can take up to 6 months and construction up to a year. Furniture is ordered and delivered during construction, and install takes one day once the home is finished. Design-build projects with design, build and furnishing run $500K and up.

Interior design fees

Design fees start at $3,500 per room, and we share your flat design fee on the first call. That way you know the cost and the calendar before you commit to anything. See our services page for what each path includes, and our furnishing-only vs full-service guide if you are not sure which one fits.

Where the time in an interior design project actually goes

Kitchen breakfast nook with stone arch in a Scottsdale remodel
Saguaro Reserve, North Scottsdale. Designed and built by Living with Lolo.
Most clients picture construction as the long part. In practice, three things set the calendar.
  1. Design decisions. Most decisions happen early, before anything is ordered or built. A week of indecision here can move the finish date by more than a week, because orders wait on approvals.
  2. Lead times on custom pieces. Custom upholstery, cabinetry, stone and lighting are made to order. The longest-lead item sets the install date for the whole room.
  3. Permits and inspections. Any remodel that moves walls, plumbing or electrical also needs permits. Because Living with Lolo is a licensed general contractor, we pull them ourselves instead of handing that step to another firm.
In a remodel, construction typically takes 4 to 6 months of the 6 to 8 month all-in window, with furniture ordering and delivery running alongside it. As one example, our Desert Oasis remodel in Scottsdale had a 6-week design phase and a 16-week installation. Our whole-home remodel guide walks through each phase, and the kitchen remodel timeline breaks down a single room.

What the data shows about build and remodel timelines

National numbers help explain why local timelines look the way they do.
  • The U.S. Census Bureau's Survey of Construction tracks how long new homes take from permit to finish (Census, Length of Time tables).
  • NAHB's analysis of that survey, published September 8, 2026, found a new single-family home took 8.8 months on average in 2025, and homes built by a hired contractor took about 11.7 months (NAHB Eye on Housing, 2026).
  • The same analysis found larger homes take longer: about 10.7 months for 4,000 to 4,999 square feet and 16.3 months for homes over 6,000 square feet. The Mountain division, which includes Arizona, averaged 9.1 months.
However, those figures stop when the floors are in. They do not include design before the permit, or furnishing after. That is why our 12 to 24 month range for a new build in North Scottsdale or Paradise Valley runs longer than the national average. It covers the whole home, ready to live in.

How we plan around when you want to be back

Many of our clients live somewhere else for at least part of the year. So the most useful question on a first call is often not "how long" but "when do you want to walk in?" We build the schedule backward from that date.
Primary bedroom sitting area ready for move-in, Scottsdale
Saguaro Reserve, North Scottsdale. Designed and built by Living with Lolo.
  1. Pick the arrival date. Holidays, the start of the winter season or a family visit.
  2. Count back the project length. About 6 to 8 months all-in for furnishing or a remodel, 12 to 24 for a new build. For furnishing, that is 6 weeks of design, 4 to 6 months of ordering and delivery, and a one-day install.
  3. Lock the design early. Approvals happen by video if you are out of state, so you do not need to fly in for each decision.
  4. Order the longest-lead pieces first. For example, custom sofas, stone and lighting go in first.
  5. Install while you are away. Install takes one day. We deliver, install and style furniture, rugs and accessories before you land.
If you want to be in by the winter season, starting design by early spring gives a furnishing project its 6 to 8 months. For month-by-month detail, including summer heat, monsoon season and permitting, read our best time to remodel in Scottsdale guide. Our second-home interior design page shows how this works for owners in Silverleaf, DC Ranch and Paradise Valley.

A sample calendar for an October arrival

"By October would be great" is one of the most common things we hear. Here is roughly how that works for each type of project. Of course, exact months depend on your scope and the pieces you choose.

Furnishing only (about 6 to 8 months all-in), arriving in October

  1. February: First call, walkthrough in person or by video, and your flat design fee.
  2. February to mid-March (design, about 6 weeks): Concepts, selections and approvals. You approve furniture, lighting, rugs and window treatments, usually in one or two meetings.
  3. Mid-March: Orders placed, longest-lead custom pieces first.
  4. April to September (ordering and delivery, 4 to 6 months): Furniture lead times set the pace while pieces are made and shipped. We track every order and receive each piece before install day.
  5. Late September: Install day, the reveal. We deliver, place, hang and style everything in one day, then do a final walkthrough by video.
  6. October: You arrive to a finished home.

Remodel with furnishing (6 to 8 months all-in), arriving in October

  1. February: First call, scope and design fee.
  2. March: Design, about 6 weeks: finishes, drawings and furniture selections. We submit permits once you approve the drawings, and we order furniture right away so its 4 to 6 months of lead time runs alongside construction.
  3. April to September: Permits and construction, 4 to 6 months. Furniture ordering and delivery happen at the same time, so pieces are ready when construction ends.
  4. Late September: Final inspections and cleaning, then install day: one day to deliver, place and style everything.
  5. October: Move-in.
The summer months are a good fit for this, because many owners are away and our team can work in the house while it is empty. If you are already past these start dates, it is still worth a call. We may phase the work, choose in-stock pieces for the rooms you use first, or set a new target date you can count on.

What can shorten or stretch the timeline

What helps:
  1. A clear scope before design starts.
  2. Quick approvals, even by video.
  3. Choosing in-stock pieces for rooms with a firm deadline.
  4. One team for design and construction, so drawings and bids do not travel between firms.
Where delays come from:
  1. Changing the scope after orders are placed.
  2. Custom or imported pieces with long production times.
  3. Permit corrections and HOA reviews, common in gated Scottsdale communities.
  4. Hiring a designer and a contractor separately, then coordinating them yourself.
That last point is the one we hear most. One client asked, "Do I hire a designer first? Who helps this whole thing come together?" Our design-build vs hiring separately guide explains why one team usually keeps the calendar shorter.

Real Scottsdale interior design timelines from our work

Saguaro Reserve, a 4,281-square-foot modern desert home in North Scottsdale, was redesigned and rebuilt by Living with Lolo as a full remodel, with one team handling design and construction. Desert Interlude is a Scottsdale second-home condo furnished and finished for owners who live out of state. Browse more in our portfolio. Each of these two projects took 8 months from start to finish, all phases included, which is the top of our 6 to 8 month all-in range. Every home is different, and your timeline will depend on your scope.

Why one team keeps the calendar honest

Lauren Lerner started Living with Lolo so clients would not have to manage two firms through a luxury project. Living with Lolo is a luxury interior designer in Scottsdale and a licensed general contractor, voted PHOENIX magazine Best of the Valley Readers' Choice, Interior Design category, four years in a row (2023 through 2026). Because the same team designs, builds and furnishes, the schedule Lauren Lerner gives you on the first call is the one the whole team works from. We serve Scottsdale, Paradise Valley, Arcadia, Silverleaf, DC Ranch and the greater Phoenix area. See how the steps fit together on our process page.

Ready to Talk Through Your Timeline?

Tell us when you want to be back, and we will tell you what is realistic.
Book a Discovery Call

How Long Does Interior Design Take? Common Questions

How long interior design takes

How long does interior design take in Scottsdale?
It depends on the phases. A furnishing project with Living with Lolo is about 6 weeks of design, 4 to 6 months of ordering and delivery and a one-day install, so about 6 to 8 months all-in. A remodel is about 6 weeks of design and 4 to 6 months of construction, with furniture ordered and delivered during construction, so it also lands at about 6 to 8 months all-in. A new build takes 12 to 24 months all-in: about 6 weeks of design, permits that can take up to 6 months and construction that can take up to a year, with furniture ordered during construction. All-in means from the first design meeting to move-in, furnishings included.
Can my home be ready by a specific date?
Often, yes, if we start early enough. We plan backward from your arrival date, order the longest-lead pieces first and install while you are away. For a winter arrival, starting design by early spring gives a furnishing project its 6 to 8 months. See our best time to remodel in Scottsdale guide for month-by-month detail.

Remodel and furnishing timelines

Is a remodel a year-plus process?
Usually not. A remodel with Living with Lolo typically takes about 6 to 8 months all-in, any size, including furnishing: about 6 weeks of design, then 4 to 6 months of construction, then a one-day install. Furniture is ordered and delivered during construction, which is why a remodel takes about as long as furnishing alone. A large kitchen remodel on its own is shorter, about 4 to 6 months all-in. New builds are the projects that run 12 to 24 months.
Why does a furnishing project take months if install is only one day?
Because most of the time is ordering and delivery. Design takes about 6 weeks. Then custom furniture takes 4 to 6 months to be made and shipped, and the longest lead time sets the install date. Once everything has arrived, we install it all in one day, so the house goes from empty to finished at once.

Planning, travel and cost

Do I need to be in Arizona during the project?
No. Many of our clients live out of state for part of the year. We meet by video, walk the house for you on video at each stage and handle delivery, installation and styling while you are away.
What slows a project down the most?
Changing the scope after orders are placed, custom pieces with long production times and permit corrections. Hiring a separate designer and contractor adds handoffs too. Living with Lolo pulls permits in-house under Arizona ROC #347577, which removes one of those handoffs.
How much does a project cost?
Furnishing starts at $75K, with a three-room minimum. Most projects with design, build and furnishing run $500K and up. Design fees are separate, start at $3,500 per room, and we share your flat design fee on the first call.
Lauren Lerner, founder and principal designer of Living with Lolo
Lauren Lerner
Principal Designer, Living with Lolo
Lauren Lerner is a luxury interior designer in Scottsdale who is a licensed general contractor, and the founder and principal designer of Living with Lolo (Arizona ROC #347577). Living with Lolo was voted PHOENIX magazine Best of the Valley Readers' Choice, Interior Design category, four years in a row (2023 through 2026). Her work has appeared in Architectural Digest, House Beautiful, and The Wall Street Journal. Learn about Lauren and the studio.

About Living with Lolo

Living with Lolo is a Scottsdale, Arizona-based luxury interior design and construction firm. The company specializes in full-service interior design, design-build remodeling, and construction-led renovations for high-end residential homes in Scottsdale, Paradise Valley, and Phoenix. Living with Lolo manages both interior design and licensed general contracting under one roof, guiding projects from concept through construction and white-glove installation.